Project Overview
The Nam Kap Hydropower Project is a 12 MW run-of-the-river power plant located in Xaysomboun province, 35 km northeast of Vang Vieng. The plant had been experiencing persistent operational issues, affecting power generation and system reliability.
The Challenge
Unstable Load Performance
Plant operators reported that both Unit 1 and Unit 2 experienced simultaneous load drops when operating at 6 MW, significantly impacting power production. After a thorough investigation, our team identified three major causes:
1.1 Faulty Pressure Transmitter
1.2 Insufficient Water Flow
1.3 Profibus Data Transmission Failures
The Solution
Precision Engineering & System Optimization
Our team implemented a structured troubleshooting and repair plan to address each issue systematically.
1.1 Pressure Transmitter Calibration & Replacement
1.2 Water Flow Restoration
1.3 Profibus Communication System Enhancement
1.4 PLC System & Hardware Upgrades
1.5 Software & Programming Enhancements
The Result: A Fully Optimized & Stable Hydropower System
Long-standing load drop issues were completely eliminated.
Conclusion
Committed to Excellence in Hydropower Solutions
At NB Lao Sole Co., Ltd, we take pride in delivering high-performance solutions, resolving complex technical challenges efficiently, and ensuring hydropower plants operate with maximum stability and reliability.